Blue line to Barkarby
- Preparatory works – DoneThe programme broke ground in Barkarby in March 2019. Source
- Tunnel excavation – DoneThe tunnels between Akalla and Barkarby have been fully excavated since 2023. Source
- Station construction – In progressBuilding and installation works are under way at both stations, above and below ground. The programme’s first escalators are in place at Barkarbystaden. Source
- Track and railway systems – In progressThe first rail was laid at Barkarbystaden station in June 2026 and track laying continues along the full stretch. Source
Status by station
- BarkarbystadenFit-out and installationsThe concrete works are done. The station and its entrances are now being completed and fitted out, with technical installations in the tunnels and above ground – and track laying in the tunnels has begun. Source
- BarkarbyFit-out and installationsAll concrete works are done. The station and its two entrances in Veddesta are being completed and fitted out, with technical installations both above and below ground. Source